A Reference for Architects, Builders & Spec Writers

AV and Low-Voltage Pre-Wire Specification

This is the residential rough-in standard we work to in Greater Cincinnati, published so your team can draw and bid against it without waiting on us. It covers what to run, where to leave access, and when each decision has to be made. The figures below are our standard practice — we confirm every one of them against the actual plan set before rough-in.

How to Use This Document

Architects and engineers: lift the room-by-room table into your drawing notes. Spec writers: the short-form language further down is written to be edited into your project manual. Builders and superintendents: the five milestones are the dates we will ask you for.

Structured wiring and equipment rack for a new construction home by Phantom Sound in Cincinnati
Sequence

Five Milestones That Decide How This Goes

Pre-wire is less about cable than about timing. Each milestone closes a window, and once it passes the same change costs materially more. The dates belong to you; we schedule backward from them.

01

Design Development

Locations go on the plans: displays, speakers, keypads, cameras, access points, the head-end, and conduit runs, marked on the architectural and electrical sets while drawings are still moving. This is the only milestone at which changes are free.

02

Pre-Rough-In Walk

We walk the framed shell with the electrician and the superintendent. Line-voltage and low-voltage conflicts, box locations, and shade pocket framing get settled standing in the room, before anything is pulled.

03

Rough-In

Cable is pulled, boxes and back boxes are set, conduit and sleeves are installed, and every run is labeled at both ends. Nothing is spliced inside a wall and nothing is daisy-chained.

04

Pre-Drywall Verification

A documented walk against the device schedule, photographed before the walls close. This is the last moment a missing run costs tens of dollars instead of thousands, and it is the record you want years later if a wall is ever opened.

05

Trim and Commissioning

Devices installed, the network tested and certified, the system programmed, and the owner trained. As-built documentation and a labeled rack schedule are handed over at closeout.

Room-by-Room Rough-In Schedule

What we ask to have run and left accessible, by location. Quantities are our standard baseline for a custom home; we confirm each one against the plan set and the scoped system before rough-in.

LocationCategory cableAudio & videoConduit, boxes & accessPower & coordination
Great room / primary display wall2 × Cat6AOne home-run pair per in-ceiling or in-wall speakerRecessed low-voltage box behind the display; 1 in. minimum conduit to the nearest concealed equipment locationRecessed receptacle behind the display. Display height set on site from the seated sightline, not a fixed dimension
Kitchen1 × Cat6AOne home-run pair per speakerStandard low-voltage box for the keypad; back boxes where cabinetry or soffit will block later accessNeutral at every switch and keypad location
Primary suite2 × Cat6A at the display wallOne home-run pair per speakerRecessed box behind the display; conduit where the display wall has no accessible cavityReceptacle behind the display; shade power at the window heads
Dedicated theater / media room2 × Cat6A at the display and at the rackOne pair per speaker position including surrounds and heights; dedicated subwoofer lines2 in. sleeve from the room to the head-end; back boxes at every in-ceiling position; for projection, conduit from the lens position to the equipment locationDedicated circuit for amplification. Coordinate riser and platform framing before rough-in
Home office and desk locations2 × Cat6A per desk wall—Standard low-voltage boxReceptacle at desk height
Secondary bedrooms1 × Cat6A per display wallOne pair per speaker where scopedRecessed box behind the displayReceptacle behind the display
Ceilings — wireless coverage1 × Cat6A to each access point position—Low-voltage ring or bracket at the ceiling; hold clear of HVAC runs and recessed cansAccess points are powered over Ethernet; no local power required
Patio and outdoor living1 × Cat6A for control and any outdoor displayOne pair per speaker; direct-burial rated where buriedSleeve from interior to exterior below grade or through the band joist; weatherproof boxesGFCI receptacle at the display. Coordinate with the landscape and hardscape trades
Exterior — cameras and door stations1 × Cat6A per camera and per door station—Box at each soffit or wall position; verify soffit depth before trimPowered over Ethernet. Coordinate positions against final grade and mature plantings
Window heads — motorized shades——Recessed pocket with a removable access panel. Verify pocket depth against the fabric roll diameter before framingPower at each window head. Whether that is line or low voltage depends on the product — confirm before rough-in
Head-end / equipment roomEvery run home run and labeled at both ends—24 in. minimum clear depth with front access; 2 in. sleeves to the attic and to the basement or crawlTwo or more dedicated 20-amp circuits. Conditioned space with a return-air path
Lighting control——Keypad boxes ganged with the switch boxes they replace; panel location coordinated with the electricianNeutral required at every switch and keypad location

Cable standards applied throughout. Category cable is Cat6A in a star topology, home run to a single head-end — no in-wall splices, no daisy-chained runs, no shared drops. Speaker cable is 16 AWG stranded copper minimum, 14 AWG on extended runs, one home-run pair per speaker, never looped. Plenum-rated cable where code requires it.

Every run is labeled at both ends at rough-in, verified against the device schedule before drywall, and tested and certified at trim.

Short-Form Specification Language

Written to be edited. Drop it into your project manual, renumber to your office master, and strike anything the project does not carry. Section numbering is left generic on purpose — see the MasterFormat note in the questions above.

Part 1 — General

1.01 Summary. Furnish and install a complete residential low-voltage infrastructure comprising structured cabling, audio-video systems, wireless network infrastructure, and rough-in provisions for lighting control, motorized window treatments, and video surveillance, as indicated on the Drawings and in the Device Schedule.

1.02 Related requirements. Division 26 Electrical — line-voltage rough-in, lighting control panel and keypad boxes, neutral conductors at switch locations, and dedicated circuits at the head-end. Division 28 Electronic Safety and Security — surveillance and access devices. Mechanical — conditioned air and return-air path at the head-end.

1.03 Submittals. (a) Marked-up plan set indicating every device location. (b) Device Schedule listing each cable run with origin, destination, cable type, and responsible trade. (c) Head-end elevation stating clear depth, access, continuous heat load, and circuit requirements. (d) Product data for all equipment. (e) At closeout: as-built run list, labeled rack schedule, network configuration, device inventory with models and serial numbers, and a record of Owner training.

1.04 Quality assurance. Installer shall be a manufacturer-authorized dealer for each specified control, lighting, and audio platform; shall employ technicians holding the CEDIA Integrated Systems Technician credential; shall be licensed and insured; and shall perform the installation with its own employees.

1.05 Coordination. Attend a pre-rough-in walk-through with the Electrical Contractor and the Superintendent. Attend a pre-drywall verification walk against the Device Schedule and photograph all runs before walls are closed. Schedule deliverables against the Contractor’s rough-in, drywall, and trim dates.

Part 2 — Products

2.01 Basis of design. Control and automation: Control4; Josh.ai where natural-language voice control is required. Lighting control and motorized shading: Lutron. Audio distribution and loudspeakers: Sonos, Sonance, Klipsch. Network infrastructure: Araknis. Video displays: Sony, Samsung. Substitutions permitted only where the substituted platform delivers equivalent integration across every specified subsystem.

2.02 Cable. Horizontal data cable: Category 6A, home run, star topology to a single head-end. Loudspeaker cable: 16 AWG stranded copper minimum, 14 AWG on extended runs, one home-run pair per loudspeaker. Riser- or plenum-rated as required by code and by the installed condition.

Part 3 — Execution

3.01 Rough-in. Install in accordance with the Device Schedule. Label every run at both ends. Do not splice within walls. Do not daisy-chain data or loudspeaker runs. Provide back boxes at in-ceiling loudspeaker positions where acoustic or fire separation is required.

3.02 Head-end. Provide a minimum 24 inches clear depth with front access. Coordinate dedicated 20-amp circuits and a conditioned return-air path.

3.03 Window treatments. Verify shade pocket depth against the specified fabric roll diameter before framing. Coordinate power at window heads and confirm line- or low-voltage requirement by product.

3.04 Testing and closeout. Test and certify every data run. Program and commission all systems. Train the Owner. Submit as-built documentation.

Offered as a starting point for your project manual, not as a sole-source specification. The quality-assurance bar above is written so more than one qualified integrator can meet it — we would rather be compared on a defined scope than win on a vague one.

"

A category cable costs a few dollars during framing and a few thousand after drywall. Nothing else in the house has that ratio.

— Phantom Sound pre-wire standard

Submittals

What We Issue, and When

✓

Marked-up plan set

Display, speaker, keypad, camera, access point, and head-end locations on your drawings. Issued at design development, while the set is still changing.

✓

Device schedule and rough-in checklist

Every run with its origin, destination, cable type, and the trade responsible for it. Issued before rough-in and reused as the pre-drywall verification list.

✓

Head-end elevation and power requirements

Rack or enclosure layout, clear depth and access requirements, continuous heat load, and the dedicated circuits we need from the electrical scope.

✓

As-built documentation at closeout

Final run list, labeled rack schedule, network configuration, device inventory with models and serial numbers, and a record of owner training.

Specification Questions

For Architects, Engineers, and Spec Writers

Where does this scope sit in MasterFormat?

Most of it falls in Division 27, Communications — structured cabling, audio-video systems, and the head-end. Surveillance and security devices fall in Division 28, Electronic Safety and Security. Lighting control sits with the electrical scope in Division 26, but its keypad boxes, panel location, and neutral requirements still have to be coordinated with us. We deliberately do not prescribe six-digit section numbers: they move between MasterFormat editions and most offices renumber to their own master anyway.

Can this scope be bid competitively?

Yes, and we prefer it that way. The device schedule and rough-in checklist are written so another integrator can price the identical scope. We would rather be compared on a defined scope than win on a vague one.

Who provides the conduit and boxes, you or the electrician?

It varies by project, so we make it explicit in the schedule instead of assuming. Most commonly the electrician sets line-voltage boxes and we set low-voltage boxes, conduit, and sleeves. What matters is that one document says who does which before rough-in starts.

What does the head-end need from the electrical scope?

A dedicated, conditioned space with front access, and dedicated 20-amp circuits sized to the equipment list we issue. This equipment generates heat continuously, so a closet with no return-air path will shorten the life of everything inside it.

Does any of this apply to a remodel?

Much of it does, but the sequence compresses and access governs everything, which makes the plan review matter more rather than less. We work out what can be reached from an attic, a basement, or an existing chase before committing to a scope. See also new construction AV and pre-wire.

Have Us Review Your Set

Send the architectural and electrical sets. We return this specification applied to your project: marked locations, a device schedule, and the rough-in dates we need from your superintendent.